Reconstruction Timeline Planner

Track the standard phases of build-back after a mitigation loss.

Overall Build Progress 0%
1

Mitigation & Tear-Out

3-5 Days

Initial water extraction, removal of non-salvageable wet materials (drywall/flooring), and structural drying using commercial dehumidifiers.

2

Estimating & Approvals

1-3 Weeks

The contractor drafts a scope of work in Xactimate and submits it to the insurance adjuster for approval before reconstruction begins.

3

Building Back

2-6 Weeks

The physical rebuild of the property begins. Subcontractors are scheduled for framing, drywall, electrical, and flooring installation.

4

Finishing Touches

3-5 Days

Trim work is installed (baseboards, casing) and the final punch list is generated to ensure the property is fully returned to pre-loss condition.